Has the permit request been submitted? Do you expect objections?  

The environmental permit application was submitted 9 February 2024. Two others will follow. Once the permit request is officially submitted the ministry EZK will communicate through their official channels i.e. RVO and https://www.rvo.nl/onderwerpen/bureau-energieprojecten/lopende-projecten/aramis

We follow the official process of the RCR (Rijkscoordinatieregeling, together with Aramis). Like any other permit request, there is always the option for stakeholders to review the requests. Publication of draft permits is expected in September 2024. The general public and advisors can give their comments and the Ministry of EZK will take these comments into account in the final decision on the permit (expected in 2025).